Chen Taylor

5 interactions

← Back to Contacts

Contact Details

Subcontractor:

Lewis Builders

Created: 11/28/2025 • Updated: 11/28/2025

📞Call(445s)

Discussion:

Site walk-through discussion. Reviewed existing conditions, access points, and staging areas.

Action Items:

Complete site visit and document existing conditions.

📧Email

San Jose Convention Center Expansion - Site Visit Scheduling

We would like to schedule a site visit. Our team is available Tuesday or Wednesday afternoon.

📞Call(500s)

Discussion:

Pre-qualification call to review company background, recent projects, and references.

Action Items:

Provide updated references from recent projects.

📞Call(622s)

Discussion:

Follow-up on submitted proposal. Clarified pricing questions and discussed value engineering options.

Action Items:

Revise pricing to include value engineering alternates discussed.

📞Call(569s)

Discussion:

Pre-qualification call to review company background, recent projects, and references.