Hoa Zhang

7 interactions

← Back to Contacts

Contact Details

Subcontractor:

Baker & Sons Concrete

Created: 11/28/2025 • Updated: 11/28/2025

💬Text

Our bid is ready for submission. Should we email it or upload to the portal?

💬Text

Yes, we are very interested in this project. When can we schedule a site walk?

💬Text

Thanks for sending the plans. Reviewing now.

📞Call(396s)

Discussion:

Went over bid package details and specifications. Answered questions about project phasing.

Action Items:

Send material samples and cut sheets for approval.

📞Call(240s)

Discussion:

Discussed project scope, timeline, and key milestones. Reviewed site conditions and access requirements.

Action Items:

Submit proof of insurance and bonding letter by end of week.

📞Call(876s)

Discussion:

Site walk-through discussion. Reviewed existing conditions, access points, and staging areas.

Action Items:

Complete site visit and document existing conditions.