Jose Singh
25 interactions
Contact Details
Created: 11/28/2025 • Updated: 11/28/2025
Discussion:
Discussed project scope, timeline, and key milestones. Reviewed site conditions and access requirements.
Action Items:
Submit proof of insurance and bonding letter by end of week.
Napa Valley Winery Resort - Insurance and Bonding Documentation
Attached please find our current insurance certificates and bonding capacity letter as requested.
Discussion:
Follow-up on submitted proposal. Clarified pricing questions and discussed value engineering options.
Discussion:
Site walk-through discussion. Reviewed existing conditions, access points, and staging areas.
Action Items:
Complete site visit and document existing conditions.
Oakland Cultural Arts Center - Bid Submission
Thank you for the opportunity to bid on this project. Please find our comprehensive proposal attached.
Fremont Industrial Complex - Scope Clarification Request
Following up on our conversation regarding scope clarification. Please confirm our understanding is correct.
Discussion:
Follow-up on submitted proposal. Clarified pricing questions and discussed value engineering options.
Action Items:
Revise pricing to include value engineering alternates discussed.
Fremont Industrial Complex - RFI Response - Clarifications Needed
Per our phone conversation, please find responses to the RFIs below. Let me know if you need any clarification.
Discussion:
Discussed project scope, timeline, and key milestones. Reviewed site conditions and access requirements.
Discussion:
Follow-up on submitted proposal. Clarified pricing questions and discussed value engineering options.
Action Items:
Revise pricing to include value engineering alternates discussed.
Yes, we are very interested in this project. When can we schedule a site walk?
Confirmed for the site meeting on Tuesday at 10am.
Discussion:
Site walk-through discussion. Reviewed existing conditions, access points, and staging areas.
Action Items:
Complete site visit and document existing conditions.
Fremont Industrial Complex - RFI Response - Clarifications Needed
Per our phone conversation, please find responses to the RFIs below. Let me know if you need any clarification.
Fremont Industrial Complex - RFI Response - Clarifications Needed
Per our phone conversation, please find responses to the RFIs below. Let me know if you need any clarification.
Oakland Cultural Arts Center - Bid Submission
Thank you for the opportunity to bid on this project. Please find our comprehensive proposal attached.
Discussion:
Discussed project scope, timeline, and key milestones. Reviewed site conditions and access requirements.
Action Items:
Submit proof of insurance and bonding letter by end of week.
We can meet the schedule you outlined.
Napa Valley Winery Resort - RFI Response - Clarifications Needed
Per our phone conversation, please find responses to the RFIs below. Let me know if you need any clarification.
We can meet the schedule you outlined.
Napa Valley Winery Resort - Site Visit Scheduling
We would like to schedule a site visit. Our team is available Tuesday or Wednesday afternoon.
Fremont Industrial Complex - Insurance and Bonding Documentation
Attached please find our current insurance certificates and bonding capacity letter as requested.
Confirmed for the site meeting on Tuesday at 10am.
Confirmed for the site meeting on Tuesday at 10am.
Discussion:
Discussed project scope, timeline, and key milestones. Reviewed site conditions and access requirements.
Action Items:
Submit proof of insurance and bonding letter by end of week.